Buckingham County planners have endorsed a zoning permit for a natural gas compressor station to serve the proposed Atlantic Coast Pipeline as it slices through the heart of Virginia.

The Planning Commission vote on Monday night to recommend approval of a special-use permit for the station will move the intensifying public battle over the project to the Board of Supervisors to settle.

The vote was 7-0 with one abstention. Supervisor Representative Danny R. Allen abstained because he is a Dominion employee.

Aaron Ruby, a spokesman for the pipeline company, commended the commission on its vote. “We appreciate the thoughtful, deliberative way the commission went about its work,” Ruby said.